CHEKU WATER PROJECT REPORT ON 30 SEP’09.


The second phase of the water project complied in primary stage, the last point was to do back fill, to put fill sand down into the well from the point of 79 meters deep to 110 meters, and it’s done.


The bottom of the well capping , the cap will be opened the time pump testing department from the Hydro Tech will arrival at water project site.


Pump testing will be done; the exercise will give us the result quantity of the water, how much water yield per hour, this result will tell us the size of the water engine needed to be bought.

Water will be taken to the Government water laboratory, in this stage will be telling by results if water will be safe for human being useful or not.


Physical the water test was sweet, myself I tested, drilling team and many local community was around tested it too. In other few areas result of water have been found to much salts, in this results community not happy since it’s very hard to drinks water having salts. In our water project were very lucky.


I talked to Mr. Bago today on 30thSep’09, he is in Tanga Region where his Mother admitted in the Regional hospital, he told me that by Saturday he will be in Dodoma, so he asked me to contact him since we hope by next week the pump testing department from Hydro Tech probably they will be there, in case I will let him know and then he need to come at the water project site.


My comments, now the community waiting for a very sensitive stage which is pump testing, and to get a water safeties, final stage of pump and engine installation and enjoying the fruits of Queen Victoria Water Project in Canada. WATER.


Moshi R. Changai

PROJECT MANAGER

CHEKU WATER PROJECT